Proposition 14 Project Detail

Data updated on: 9/02/2014 11:01AM Print This Page
Project Summary
Project ID 212104088 TxDOT District El Paso County Name El Paso Funding Status Funded
Highway IH 10 Project Length .750 Miles Project Type Proposition 12 v2 Bid Date 2012-Oct
Work From IH 10 @ LP 375 Low Bid Amount $42,550,974.83
Work To .
Description CONSTRUCT FREEWAY RAMPS
Show Project Location
Contact Information
TxDOT Contact Celia Salazar, P.E. Phone: (915)-790-4400
Construction Company J.D. ABRAMS, L.P.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
12/20/2012 04/15/2013 460 337 73.26 % 80.04 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $2,084,997.76 $2,534,657.39
Construction $43,427,789.28 $36,016,921.83
Construction EngineeringConstruction Engineering Definition $1,996,946.02 $1,137,520.05
Contingency Contingency Definition $1,288,337.74
Indirect Indirect Definition $3,340,251.52
Total Cost $52,138,322.32 $39,689,099.27