Project ID 212102137 TxDOT District El Paso County Name El Paso Funding Status Funded
Highway IH 10 Project Length 5.164 Miles Project Type Proposition 14 Bid Date 2014-Oct
Work From MESA STREET Low Bid Amount $158,778,403.48
Work To EXECUTIVE CENTER
Description CONSTRUCT INTERCHANGE
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Celia Salazar, P.E. Phone: (915)-790-4400
Construction Company TRADECO INFRAESTRUCTURA, INC.
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 01/2012 12/2012 09/2013 04/2014 03/2013 03/2014 03/2014 04/2014
Actual Date 01/2012
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $7,554,674.90 $9,069,144.75
Construction $153,904,607.02 $0.00
Construction EngineeringConstruction Engineering Definition $7,552,704.44 $0.00
Contingency Contingency Definition $1,891,639.86
Indirect Indirect Definition $8,849,762.02
Total Cost $179,753,388.24 $9,069,144.75