Proposition 14 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 152401041 TxDOT District Houston County Name Brazoria Funding Status Funded
Highway SH 332 Project Length .569 Miles Project Type Proposition 14 Bid Date 2009-Mar
Work From 0.373 MI N OF THIS WAY STREET Low Bid Amount $63,360,228.48
Work To 0.196 MI S OF THIS WAY STREET
Description CONSTRUCT OVERPASS/UNDERPASS
Show Project Location
Contact Information
TxDOT Contact Bill Brudnick, P.E. Phone: (713) 802-5617
Construction Company WILLIAMS BROTHERS CONSTRUCTION CO., INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
05/06/2009 06/22/2009 963 950 97.44 % 100.03 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $3,908,726.66 $2,350,465.60
Construction $82,715,174.00 $68,999,790.06
Construction EngineeringConstruction Engineering Definition $3,190,797.27 $1,887,759.93
Contingency Contingency Definition $4,786,195.89
Indirect Indirect Definition $3,326,406.14
Total Cost $97,927,299.96 $73,238,015.59