Proposition 14 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
070003014 |
TxDOT District |
Austin |
County Name |
Travis |
Funding Status |
Funded |
| Highway |
SH 71 |
Project Length |
1.524 Miles |
Project Type |
Economic Stimulus |
Bid Date |
2010-Feb |
| Work From |
0.27 MI EAST OF RO DRIVE |
Low Bid Amount |
$8,080,390.25 |
| Work To |
1.4 MI WEST OF BEE CREEK |
| Description |
CONSTRUCT CENTER TURN LANES |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Walter Barfield, P.E. |
Phone: |
(512) 832-7136 |
| Construction Company |
AUSTIN BRIDGE & ROAD, LP |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
08/2008 |
04/2009 |
08/2009 |
10/2009 |
10/2009 |
10/2009 |
|
10/2009 |
| Actual Date |
08/2008 |
04/2009 |
07/2009 |
09/2009 |
10/2009 |
10/2009 |
|
10/2009 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 04/08/2010 |
06/07/2010 |
369 |
670 |
100.00 % |
101.27 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$433,573.74 |
$220,853.83 |
| Construction |
$9,051,419.79 |
$10,126,455.97 |
Construction Engineering |
$446,055.69 |
$823,559.17 |
Contingency
 |
$575,875.55 |
|
Indirect
 |
$581,342.76 |
|
| Total Cost |
$11,088,267.53 |
$11,170,868.97 |
|
 |