Proposition 14 Project Detail

Data updated on: 7/01/2014 10:05AM Print This Page
Project Summary
Project ID 061006076 TxDOT District Atlanta County Name Bowie Funding Status Funded
Highway IH 30 Project Length 2.733 Miles Project Type Proposition 14 Bid Date 2010-Aug
Work From SPUR 86 Low Bid Amount $15,994,499.70
Work To FM 560
Description CONSTRUCT OVERPASS/UNDERPASS
Show Project Location
Contact Information
TxDOT Contact Dennis M. Beckham, P.E. Phone: (903) 799-1222
Construction Company EAST TEXAS BRIDGE, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
10/07/2010 04/01/2011 731 764 102.69 % 109.89 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $769,306.20 $782,485.84
Construction $15,150,836.84 $19,978,209.99
Construction EngineeringConstruction Engineering Definition $706,505.69 $1,241,422.94
Contingency Contingency Definition $1,020,508.22
Indirect Indirect Definition $959,277.72
Total Cost $18,606,434.67 $22,002,118.77