Proposition 14 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 052009031 TxDOT District Tyler County Name Anderson Funding Status Funded
Highway LP 256 Project Length 1.574 Miles Project Type Proposition 14 Bid Date 2009-Sep
Work From US 79 IN PALESTINE, SE & S Low Bid Amount $7,615,569.93
Work To US 84
Description CONSTRUCT NEW ROADWAY LANES
Show Project Location
Contact Information
TxDOT Contact Vernon Webb, P.E. Phone: (903) 510-9296
Construction Company SAFECO INSURANCE COMPANIES
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
11/02/2009 12/02/2009 394 508 128.93 % 96.61 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $629,807.63 $993,818.15
Construction $8,908,569.00 $8,585,574.39
Construction EngineeringConstruction Engineering Definition $380,778.50 $644,447.92
Contingency Contingency Definition $495,012.05
Indirect Indirect Definition $472,165.34
Total Cost $10,886,332.52 $10,223,840.46