Proposition 14 Project Detail

Data updated on: 12/02/2014 8:49 AM Print This Page
Project Summary
Project ID 044002010 TxDOT District Austin County Name Williamson Funding Status Funded
Highway SH 195 Project Length 5.179 Miles Project Type Proposition 14 Bid Date 2012-Sep
Work From 9.271 MI S OF SH 138 Low Bid Amount $18,778,887.62
Work To IH 35
Description CONSTRUCT NEW ROADWAY LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Walter Barfield, P.E. Phone: (512) 832-7136
Construction Company SEMA CONSTRUCTION, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
11/16/2012 01/10/2013 368 479 93.37 % 84.11 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $920,165.49 $2,482,418.42
Construction $18,252,860.22 $15,031,997.07
Construction EngineeringConstruction Engineering Definition $931,432.83 $548,578.14
Contingency Contingency Definition $373,699.86
Indirect Indirect Definition $1,087,297.59
Total Cost $21,565,455.99 $18,062,993.63