Proposition 14 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
044002010 |
TxDOT District |
Austin |
County Name |
Williamson |
Funding Status |
Funded |
| Highway |
SH 195 |
Project Length |
5.179 Miles |
Project Type |
Proposition 14 |
Bid Date |
2012-Sep |
| Work From |
9.271 MI S OF SH 138 |
Low Bid Amount |
$18,778,887.62 |
| Work To |
IH 35 |
| Description |
CONSTRUCT NEW ROADWAY LANES |
| Project Note |
This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources. |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Walter Barfield, P.E. |
Phone: |
(512) 832-7136 |
| Construction Company |
SEMA CONSTRUCTION, INC. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
07/2003 |
12/2007 |
12/2008 |
08/2009 |
01/2010 |
01/2011 |
01/2011 |
01/2011 |
| Actual Date |
07/2003 |
12/2007 |
12/2008 |
08/2009 |
07/2011 |
|
|
|
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 11/16/2012 |
01/10/2013 |
368 |
75 |
14.62 % |
19.76 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$920,165.49 |
$2,620,899.36 |
| Construction |
$18,252,860.22 |
$3,998,525.51 |
Construction Engineering |
$931,432.83 |
$88,749.97 |
Contingency
 |
$373,699.86 |
|
Indirect
 |
$1,087,297.59 |
|
| Total Cost |
$21,565,455.99 |
$6,708,174.84 |
|
 |