Proposition 14 Project Detail

Data updated on: 9/02/2014 11:01AM Print This Page
Project Summary
Project ID 044001039 TxDOT District Austin County Name Williamson Funding Status Funded
Highway SH 195 Project Length 3.499 Miles Project Type Proposition 14 Bid Date 2013-Jun
Work From 4.987 MI SOUTH OF SH 138 Low Bid Amount $33,311,111.00
Work To 8.486 MI SOUTH OF SH 138
Description CONSTRUCT NEW ROADWAY LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Walter Barfield, P.E. Phone: (512) 832-7136
Construction Company SEMA CONSTRUCTION, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
07/16/2013 12/18/2013 510 166 32.55 % 36.47 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,632,244.44 $2,193,213.30
Construction $37,082,489.71 $12,286,494.28
Construction EngineeringConstruction Engineering Definition $1,652,231.11 $307,277.89
Contingency Contingency Definition $662,891.11
Indirect Indirect Definition $1,928,713.33
Total Cost $42,958,569.70 $14,786,985.47