Proposition 14 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
033812002 |
TxDOT District |
Beaumont |
County Name |
Liberty |
Funding Status |
Funded |
| Highway |
SH 105 |
Project Length |
2.770 Miles |
Project Type |
Proposition 14 |
Bid Date |
2010-Feb |
| Work From |
SH 105 WEST OF CLEVELAND, EAST |
Low Bid Amount |
$28,386,132.89 |
| Work To |
W OF FM 1010 |
| Description |
CONSTRUCT NEW ROAD |
| Project Note |
This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources. |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Phillip Lujan, P.E. |
Phone: |
(409) 898-5740 |
| Construction Company |
ZACHRY CONSTRUCTION CORPORATION |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
01/2008 |
02/2008 |
02/2008 |
01/2009 |
09/2009 |
08/2008 |
06/2008 |
10/2009 |
| Actual Date |
01/2008 |
02/2008 |
02/2008 |
01/2009 |
12/2009 |
08/2008 |
06/2008 |
10/2009 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 04/22/2010 |
05/25/2010 |
744 |
689 |
84.02 % |
99.41 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$1,395,398.85 |
$89,616.76 |
| Construction |
$30,169,186.63 |
$31,139,880.59 |
Construction Engineering |
$1,281,488.74 |
$1,331,520.30 |
Contingency
 |
$2,562,977.48 |
|
Indirect
 |
$1,677,326.37 |
|
| Total Cost |
$37,086,378.07 |
$32,561,017.65 |
|
 |