| Project ID |
033801054 |
TxDOT District |
Bryan |
County Name |
Grimes |
Funding Status |
Funded |
| Highway |
SH 105 |
Project Length |
16.487 Miles |
Project Type |
Proposition 14 |
Bid Date |
2012-Sep |
| Work From |
THE NAVASOTA CITY LIMITS |
Low Bid Amount |
$6,821,958.57 |
| Work To |
0.355 MILE W. OF THE MONTGOMERY CL |
| Description |
WIDEN ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Bob Appleton, P.E. |
Phone: |
(979) 778-2165 |
| Construction Company |
KNIFE RIVER CORPORATION - SOUTH |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
07/2010 |
01/2012 |
01/2013 |
05/2013 |
08/2012 |
05/2013 |
05/2013 |
05/2013 |
| Actual Date |
07/2010 |
01/2012 |
04/2012 |
06/2012 |
06/2012 |
06/2012 |
|
06/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 12/14/2012 |
04/22/2013 |
141 |
0 |
0.00 % |
0.04 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$334,275.97 |
$336,704.93 |
| Construction |
$7,502,150.50 |
$2,750.00 |
Construction Engineering |
$304,941.55 |
$3,991.97 |
Contingency
 |
NaN |
|
Indirect
 |
$346,555.50 |
|
| Total Cost |
$8,487,923.52 |
$343,446.90 |
|
 |