Proposition 14 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
033801052 |
TxDOT District |
Bryan |
County Name |
Grimes |
Funding Status |
Funded |
| Highway |
SH 105 |
Project Length |
1.041 Miles |
Project Type |
Proposition 14 |
District Est. Bid Date |
2015-Jun |
| Work From |
AT THE INTERSECTION OF SH 105 |
|
|
| Work To |
AND FM 1774 |
| Description |
CONSTRUCT INTERCHANGE |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Bob Appleton, P.E. |
Phone: |
(979) 778-2165 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
07/2011 |
02/2012 |
10/2012 |
05/2013 |
10/2012 |
05/2013 |
10/2013 |
10/2014 |
| Actual Date |
07/2011 |
02/2012 |
|
|
|
|
|
|
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$180,760.84 |
$691,412.29 |
| Construction |
$3,688,996.66 |
$0.00 |
Construction Engineering |
$164,898.15 |
$0.00 |
Contingency
 |
NaN |
|
Indirect
 |
$187,401.03 |
|
| Total Cost |
$4,222,056.68 |
$691,412.29 |
|
 |