Proposition 14 Project Detail

Data updated on: 7/01/2014 10:05AM Print This Page
Project Summary
Project ID 033801052 TxDOT District Bryan County Name Grimes Funding Status Funded
Highway SH 105 Project Length 1.041 Miles Project Type Proposition 14 District Est. Bid Date 2015-Jun
Work From AT THE INTERSECTION OF SH 105
Work To AND FM 1774
Description CONSTRUCT INTERSECTION IMPROVEMENTS
Show Project Location
Contact Information
TxDOT Contact Bob Appleton, P.E. Phone: (979) 778-2165
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 07/2011 02/2012 10/2012 05/2013 10/2012 05/2013 10/2013 10/2014
Actual Date 07/2011 02/2012 06/2013 10/2014
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $280,280.00 $815,418.24
Construction $5,720,000.00 $0.00
Construction EngineeringConstruction Engineering Definition $255,684.00 $0.00
Contingency Contingency Definition NaN
Indirect Indirect Definition $276,276.00
Total Cost $6,532,240.00 $815,418.24