Proposition 14 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
032605002 |
TxDOT District |
Corpus Christi |
County Name |
Nueces |
Funding Status |
Funded |
| Highway |
BS 286A |
Project Length |
.989 Miles |
Project Type |
Proposition 14 |
Bid Date |
2011-Aug |
| Work From |
HOLLY ROAD |
Low Bid Amount |
$5,480,200.76 |
| Work To |
SH 357 |
| Description |
WIDEN AND REHABILITATE ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Paula Sales-Evans, P.E. |
Phone: |
(361) 808-2222 |
| Construction Company |
HAAS-ANDERSON CONSTRUCTION, LTD. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
01/2010 |
04/2010 |
07/2010 |
10/2010 |
02/2010 |
10/2010 |
|
11/2010 |
| Actual Date |
06/2010 |
10/2010 |
04/2011 |
05/2011 |
11/2009 |
05/2011 |
|
05/2011 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 10/06/2011 |
11/14/2011 |
250 |
251 |
92.96 % |
62.27 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$268,529.84 |
$366,807.50 |
| Construction |
$4,557,985.50 |
$3,805,445.35 |
Construction Engineering |
$274,010.04 |
$238,237.79 |
Contingency
 |
$356,213.05 |
|
Indirect
 |
$392,382.37 |
|
| Total Cost |
$5,849,120.80 |
$4,410,490.64 |
|
 |