Proposition 14 Project Detail

Data updated on: 8/01/2014 2:38 PM Print This Page
Project Summary
Project ID 025502050 TxDOT District Corpus Christi County Name Jim Wells Funding Status Funded
Highway US 281 Project Length 6.582 Miles Project Type Proposition 14 District Est. Bid Date 2016-Sep
Work From 0.5 MI. NORTH OF FM 1538
Work To 1 MI. NORTH OF CR 431
Description CONSTRUCT NEW ROAD
Show Project Location
Contact Information
TxDOT Contact Paula Sales-Evans, P.E. Phone: (361) 808-2222
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date
Actual Date
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $2,133,281.09 $925,508.51
Construction $43,536,348.83 $0.00
Construction EngineeringConstruction Engineering Definition $1,989,611.14 $0.00
Contingency Contingency Definition $3,604,809.68
Indirect Indirect Definition $2,102,805.65
Total Cost $53,366,856.39 $925,508.51