Proposition 14 Project Detail

Data updated on: 9/02/2014 11:01AM Print This Page
Project Summary
Project ID 024505046 TxDOT District Tyler County Name Smith Funding Status Funded
Highway SH 64 Project Length 1.191 Miles Project Type Proposition 14 Bid Date 2013-May
Work From 0.1 MI W OF FM 2661, E Low Bid Amount $2,387,571.56
Work To 0.6 MI W OF FM 724 (NEAR CR 1184)
Description CONSTRUCT NEW ROADWAY LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Vernon Webb, P.E. Phone: (903) 510-9296
Construction Company BIG CREEK CONSTRUCTION, LTD.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
07/08/2013 08/05/2013 106 99 93.40 % 91.74 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $116,991.01 $685,389.82
Construction $2,211,381.74 $2,400,606.10
Construction EngineeringConstruction Engineering Definition $162,116.11 $148,660.06
Contingency Contingency Definition $50,139.00
Indirect Indirect Definition $129,406.38
Total Cost $2,670,034.24 $3,234,655.98