Proposition 14 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 023103103 TxDOT District Waco County Name Bell Funding Status Funded
Highway US 190 Project Length 2.837 Miles Project Type Proposition 14 Bid Date 2013-Mar
Work From WS YOUNG Low Bid Amount $9,587,760.86
Work To FM 2410 IN HARKER HEIGHTS
Description CONSTRUCT NEW ROADWAY LANES
Show Project Location
Contact Information
TxDOT Contact Andy Petter, P.E. Phone: (254) 867-2740
Construction Company BIG CREEK CONSTRUCTION, LTD.
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 05/2011 09/2011 01/2012 03/2012 03/2012 07/2013 10/2013 10/2013
Actual Date 03/2011 08/2012 10/2012 12/2012 12/2012 12/2012 12/2012
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $469,800.28 $1,195,390.85
Construction $10,442,112.59 $0.00
Construction EngineeringConstruction Engineering Definition $412,273.72 $0.00
Contingency Contingency Definition $17,257.97
Indirect Indirect Definition $416,108.82
Total Cost $11,757,553.38 $1,195,390.85