Proposition 14 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
020011100 |
TxDOT District |
Beaumont |
County Name |
Jefferson |
Funding Status |
Funded |
| Highway |
US 69 |
Project Length |
1.890 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-Jul |
| Work From |
SH 105, SOUTH |
|
|
| Work To |
700 FT SOUTH OF LUCAS DRIVE |
| Description |
CONSTRUCT FREEWAY RAMPS |
| Project Note |
This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources. |
|
 |
| Contact Information |
| TxDOT Contact |
Phillip Lujan, P.E. |
Phone: |
(409) 898-5740 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
|
|
|
|
|
|
|
|
| Actual Date |
|
|
|
|
|
|
|
|
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$1,021,256.83 |
$904,087.43 |
| Construction |
$20,841,976.23 |
$0.00 |
Construction Engineering |
$1,329,718.08 |
$0.00 |
Contingency
 |
$268,861.50 |
|
Indirect
 |
$1,196,329.44 |
|
| Total Cost |
$24,658,142.08 |
$904,087.43 |
|
 |