Proposition 14 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 020011100 TxDOT District Beaumont County Name Jefferson Funding Status Funded
Highway US 69 Project Length 1.932 Miles Project Type Proposition 12 v2 Bid Date 2013-Jul
Work From SH 105, SOUTH Low Bid Amount $27,390,861.67
Work To 700 FT SOUTH OF LUCAS DRIVE
Description CONSTRUCT FREEWAY RAMPS
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Phillip Lujan, P.E. Phone: (409) 898-5740
Construction Company APAC-TEXAS, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
10/07/2013 01/13/2014 636 58 9.05 % 16.13 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,342,152.22 $1,817,744.88
Construction $22,126,667.90 $4,603,673.83
Construction EngineeringConstruction Engineering Definition $1,747,536.97 $103,784.55
Contingency Contingency Definition $353,342.12
Indirect Indirect Definition $1,572,235.46
Total Cost $27,141,934.67 $6,525,203.26