Proposition 14 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 018606066 TxDOT District Bryan County Name Washington Funding Status Funded
Highway US 290 Project Length 3.037 Miles Project Type Proposition 14 Bid Date 2011-Jan
Work From THE BNSF RAILROAD Low Bid Amount $38,482,604.51
Work To 0.3 MILE EAST OF FM 577
Description CONSTRUCT OVERPASS/UNDERPASS
Show Project Location
Contact Information
TxDOT Contact Bob Appleton, P.E. Phone: (979) 778-2165
Construction Company WEBBER, LLC
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
04/05/2011 04/25/2011 495 512 100.00 % 97.46 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,885,205.52 $1,145,304.22
Construction $38,676,530.72 $44,346,321.97
Construction EngineeringConstruction Engineering Definition $1,731,311.19 $1,462,950.46
Contingency Contingency Definition $3,462,622.37
Indirect Indirect Definition $2,300,720.20
Total Cost $48,056,390.00 $46,954,576.65