Proposition 14 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 017802055 TxDOT District Houston County Name Brazoria Funding Status Funded
Highway SH 35 Project Length 2.602 Miles Project Type Proposition 14 Bid Date 2009-Dec
Work From HARRIS COUNTY LINE Low Bid Amount $21,717,321.19
Work To FM 518
Description WIDEN ROADWAY
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Bill Brudnick, P.E. Phone: (713) 802-5617
Construction Company TRIPLE B SERVICES, L.L.P.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
01/25/2010 03/03/2010 789 1,195 151.46 % 97.56 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $964,345.61 $4,000,147.34
Construction $23,843,094.96 $21,680,467.30
Construction EngineeringConstruction Engineering Definition $885,623.52 $1,512,408.87
Contingency Contingency Definition $1,298,149.84
Indirect Indirect Definition $999,770.55
Total Cost $27,990,984.48 $27,193,023.51