Proposition 14 Project Detail

Data updated on: 7/01/2014 10:05AM Print This Page
Project Summary
Project ID 017702053 TxDOT District Lufkin County Name San Jacinto Funding Status Funded
Highway US 59 Project Length 3.436 Miles Project Type Proposition 14 Bid Date 2010-Feb
Work From SH 150 Low Bid Amount $34,123,258.85
Work To S OF UP RR
Description CONSTRUCT OVERPASS/UNDERPASS
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Cheryl Flood, P.E. Phone: (936) 633-4349
Construction Company WILLIAMS BROTHERS CONSTRUCTION CO., INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
03/24/2010 04/01/2010 839 910 99.45 % 98.17 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,638,532.44 $1,665,627.58
Construction $41,965,660.35 $36,624,132.66
Construction EngineeringConstruction Engineering Definition $1,504,774.69 $1,653,248.23
Contingency Contingency Definition $3,009,549.39
Indirect Indirect Definition $2,217,034.72
Total Cost $50,335,551.59 $39,943,008.47