Proposition 14 Project Detail

Data updated on: 12/02/2014 8:49 AM Print This Page
Project Summary
Project ID 016211001 TxDOT District Dallas County Name Navarro Funding Status Funded
Highway SH 31 Project Length 14.060 Miles Project Type Proposition 14 District Est. Bid Date 2015-Jul
Work From 3.2 MILES WEST OF FM 2555
Work To 3.7 MILES EAST OF IH 45
Description CONSTRUCT NEW ROAD
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Maher Ghanayem, P.E. Phone: (214) 320-6691
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date
Actual Date 04/2012 08/2014
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $4,807,131.27 $7,122,021.06
Construction $98,104,719.83 $0.00
Construction EngineeringConstruction Engineering Definition $4,754,369.35 $0.00
Contingency Contingency Definition $1,663,479.21
Indirect Indirect Definition $5,631,210.92
Total Cost $114,960,910.58 $7,122,021.06