Proposition 14 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 016201056 TxDOT District Waco County Name McLennan Funding Status Funded
Highway SH 31 Project Length 7.845 Miles Project Type Proposition 14 Bid Date 2009-Mar
Work From SH 31 & US 84 WYE Low Bid Amount $55,780,217.26
Work To HILL C/L
Description CONSTRUCT NEW ROADWAY LANES
Show Project Location
Contact Information
TxDOT Contact Andy Petter, P.E. Phone: (254) 867-2740
Construction Company SAFECO INSURANCE COMPANIES
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
04/13/2009 05/13/2009 814 916 121.00 % 96.77 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $2,964,048.22 $4,871,420.50
Construction $64,936,906.95 $56,699,069.44
Construction EngineeringConstruction Engineering Definition $2,419,631.20 $1,250,412.87
Contingency Contingency Definition $3,629,446.79
Indirect Indirect Definition $2,607,152.61
Total Cost $76,557,185.77 $62,820,902.81