Proposition 14 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
016201056 |
TxDOT District |
Waco |
County Name |
McLennan |
Funding Status |
Funded |
| Highway |
SH 31 |
Project Length |
7.845 Miles |
Project Type |
Proposition 14 |
Bid Date |
2009-Mar |
| Work From |
SH 31 & US 84 WYE |
Low Bid Amount |
$55,780,217.26 |
| Work To |
HILL C/L |
| Description |
CONSTRUCT NEW ROADWAY LANES |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Andy Petter, P.E. |
Phone: |
(254) 867-2740 |
| Construction Company |
SAFECO INSURANCE COMPANIES |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
06/2004 |
05/2005 |
11/2005 |
12/2008 |
02/2005 |
12/2008 |
12/2008 |
12/2008 |
| Actual Date |
06/2004 |
05/2005 |
11/2005 |
12/2008 |
02/2005 |
12/2008 |
12/2008 |
12/2008 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 04/13/2009 |
05/13/2009 |
814 |
916 |
121.00 % |
96.77 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$2,964,048.22 |
$4,871,420.50 |
| Construction |
$64,936,906.95 |
$56,699,069.44 |
Construction Engineering |
$2,419,631.20 |
$1,250,412.87 |
Contingency
 |
$3,629,446.79 |
|
Indirect
 |
$2,607,152.61 |
|
| Total Cost |
$76,557,185.77 |
$62,820,902.81 |
|
 |