Proposition 14 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
015404030 |
TxDOT District |
Yoakum |
County Name |
DeWitt |
Funding Status |
Funded |
| Highway |
US 183 |
Project Length |
10.538 Miles |
Project Type |
Proposition 14 |
Bid Date |
2013-Feb |
| Work From |
EMIL BLANK ROAD |
Low Bid Amount |
$9,614,974.93 |
| Work To |
0.20 MI. NORTH OF US 77A |
| Description |
WIDEN ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Paul Frerich, P.E. |
Phone: |
(361) 293-4347 |
| Construction Company |
HUNTER INDUSTRIES, LTD. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
05/2012 |
06/2012 |
07/2012 |
08/2012 |
10/2012 |
09/2012 |
|
09/2012 |
| Actual Date |
05/2012 |
07/2012 |
09/2012 |
11/2012 |
10/2012 |
11/2012 |
|
11/2012 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 04/26/2013 |
|
255 |
0 |
0.00 % |
0.00 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$471,133.77 |
$144,350.88 |
| Construction |
$9,885,696.33 |
$0.00 |
Construction Engineering |
$471,133.77 |
$0.00 |
Contingency
 |
$4,807.49 |
|
Indirect
 |
$514,401.16 |
|
| Total Cost |
$11,347,172.52 |
$144,350.88 |
|
 |