Proposition 14 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
013805052 |
TxDOT District |
Tyler |
County Name |
Rusk |
Funding Status |
Funded |
| Highway |
US 259 |
Project Length |
.766 Miles |
Project Type |
Proposition 14 |
Bid Date |
2011-Jun |
| Work From |
AT FM 1798, NEAR MINDEN |
Low Bid Amount |
$5,497,236.41 |
| Work To |
. |
| Description |
CONSTRUCT OVERPASS/UNDERPASS |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Vernon Webb, P.E. |
Phone: |
(903) 510-9296 |
| Construction Company |
LONGVIEW BRIDGE AND ROAD, LTD. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
05/2009 |
01/2010 |
03/2010 |
10/2010 |
10/2010 |
10/2010 |
10/2010 |
10/2010 |
| Actual Date |
05/2009 |
09/2010 |
09/2010 |
03/2011 |
01/2011 |
03/2011 |
03/2011 |
03/2011 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 08/11/2011 |
06/04/2012 |
263 |
250 |
77.40 % |
73.89 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$269,364.58 |
$650,464.18 |
| Construction |
$4,935,555.80 |
$3,954,486.83 |
Construction Engineering |
$274,861.82 |
$185,030.22 |
Contingency
 |
$357,320.37 |
|
Indirect
 |
$362,817.60 |
|
| Total Cost |
$6,199,920.17 |
$4,789,981.23 |
|
 |