Proposition 14 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 013408030 TxDOT District Fort Worth County Name Wise Funding Status Funded
Highway US 380 Project Length 10.544 Miles Project Type Proposition 14 Bid Date 2009-Mar
Work From BU 380F Low Bid Amount $37,682,221.25
Work To DENTON C/L
Description CONSTRUCT NEW ROADWAY LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Scot D. Smith, P.E. Phone: (817) 370-6673
Construction Company J.D. ABRAMS, L.P.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
04/08/2009 06/12/2009 598 869 103.21 % 97.59 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,858,462.30 $3,395,469.57
Construction $49,856,582.88 $40,444,919.04
Construction EngineeringConstruction Engineering Definition $1,517,112.09 $1,919,052.32
Contingency Contingency Definition $2,275,668.12
Indirect Indirect Definition $2,086,029.11
Total Cost $57,593,854.50 $45,759,440.93