Proposition 14 Project Detail

Data updated on: 11/10/2014 3:25 PM Print This Page
Project Summary
Project ID 011701046 TxDOT District Bryan County Name Brazos Funding Status Funded
Highway SH 21 Project Length .690 Miles Project Type Proposition 14 District Est. Bid Date 2015-Jan
Work From TEXAS AVENUE
Work To THE SH 6 WEST FRONTAGE ROAD
Description CONSTRUCT CENTER TURN LANES
Show Project Location
Contact Information
TxDOT Contact Bob Appleton, P.E. Phone: (979) 778-2165
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date
Actual Date 10/2012 11/2013 04/2014 10/2014 09/2014 10/2014 11/2013 10/2014
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $126,966.33 $45,877.38
Construction $2,591,149.56 $0.00
Construction EngineeringConstruction Engineering Definition $115,824.39 $0.00
Contingency Contingency Definition NaN
Indirect Indirect Definition $148,731.98
Total Cost $2,982,672.26 $45,877.38