Proposition 14 Project Detail

Data updated on: 10/01/2014 8:23 AM Print This Page
Project Summary
Project ID 011301041 TxDOT District Austin County Name Gillespie Funding Status Funded
Highway US 290 Project Length .343 Miles Project Type Proposition 14 Bid Date 2012-May
Work From 0.101 MI W OF MARIPOSA DR. Low Bid Amount $2,818,664.98
Work To 0.021 MI W OF OLD SAN ANTONIO RD.
Description CONSTRUCT CENTER TURN LANES
Show Project Location
Contact Information
TxDOT Contact Walter Barfield, P.E. Phone: (512) 832-7136
Construction Company SHANNON-MONK, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
07/16/2012 10/30/2012 157 436 196.40 % 97.28 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $138,114.58 $373,255.16
Construction $2,281,156.96 $2,881,206.78
Construction EngineeringConstruction Engineering Definition $125,994.32 $335,490.80
Contingency Contingency Definition NaN
Indirect Indirect Definition $242,123.32
Total Cost $2,787,389.18 $3,589,952.74