Proposition 14 Project Detail

Data updated on: 6/03/2013 7:32 AM Print This Page
Project Summary
Project ID 010909047 TxDOT District Bryan County Name Walker Funding Status Funded
Highway SH 19 Project Length 4.745 Miles Project Type Proposition 14 Bid Date 2011-Apr
Work From SH 30 Low Bid Amount $14,172,190.27
Work To IH 45
Description CONSTRUCT NEW ROADWAY LANES
Show Project Location
Contact Information
TxDOT Contact Bob Appleton, P.E. Phone: (979) 778-2165
Construction Company SMITH & COMPANY
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
05/13/2011 06/17/2011 324 390 82.28 % 95.47 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $696,082.68 $710,857.11
Construction $15,106,992.68 $14,791,860.94
Construction EngineeringConstruction Engineering Definition $142,057.69 $706,743.89
Contingency Contingency Definition $923,374.98
Indirect Indirect Definition $849,504.98
Total Cost $17,718,013.01 $16,209,461.94