Proposition 14 Project Detail

Data updated on: 11/10/2014 3:25 PM Print This Page
Project Summary
Project ID 010202099 TxDOT District Corpus Christi County Name Nueces Funding Status Funded
Highway SH 44 Project Length .756 Miles Project Type Traditional Bid Date 2013-May
Work From AT FM 1694/SH 44 INTERSECTION Low Bid Amount $12,713,097.88
Work To .
Description CONSTRUCT OVERPASS/UNDERPASS
Show Project Location
Contact Information
TxDOT Contact Paula Sales-Evans, P.E. Phone: (361) 808-2222
Construction Company BAY LTD.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
07/31/2013 09/25/2013 302 222 73.51 % 74.04 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $622,941.80 $250,502.32
Construction $12,587,021.15 $9,995,376.36
Construction EngineeringConstruction Engineering Definition $596,244.29 $298,188.26
Contingency Contingency Definition $380,121.63
Indirect Indirect Definition $695,406.45
Total Cost $14,881,735.32 $10,544,066.94