Proposition 14 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 010202099 TxDOT District Corpus Christi County Name Nueces Funding Status Funded
Highway SH 44 Project Length .756 Miles Project Type Traditional District Est. Bid Date 2013-May
Work From AT FM 1694/SH 44 INTERSECTION
Work To .
Description CONSTRUCT OVERPASS/UNDERPASS
Show Project Location
Contact Information
TxDOT Contact Paula Sales-Evans, P.E. Phone: (361) 808-2222
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 05/2012 06/2012 10/2012 02/2013 03/2013 03/2013
Actual Date 05/2012 08/2012 11/2012 03/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $616,764.04 $254,630.59
Construction $12,587,021.15 $0.00
Construction EngineeringConstruction Engineering Definition $590,331.29 $0.00
Contingency Contingency Definition $376,351.93
Indirect Indirect Definition $688,510.06
Total Cost $14,858,978.47 $254,630.59