Proposition 14 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 008805089 TxDOT District Yoakum County Name Victoria Funding Status Funded
Highway US 59 Project Length 3.446 Miles Project Type Proposition 14 Bid Date 2013-May
Work From 0.02 MI. NORTH OF LOOP 463 Low Bid Amount $14,995,694.93
Work To 0.03 MI. NORTH OF US 87
Description CONSTRUCT FRONTAGE ROADS
Show Project Location
Contact Information
TxDOT Contact Paul Frerich, P.E. Phone: (361) 293-4347
Construction Company HUNTER INDUSTRIES, LTD.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
08/19/2013 10/03/2013 270 82 30.37 % 22.59 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $734,789.05 $302,691.93
Construction $13,167,864.38 $3,618,048.73
Construction EngineeringConstruction Engineering Definition $743,786.47 $134,848.95
Contingency Contingency Definition $298,414.33
Indirect Indirect Definition $802,269.68
Total Cost $15,747,123.91 $4,055,589.61