Proposition 14 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 008614025 TxDOT District Laredo County Name Webb Funding Status Funded
Highway SL 20 Project Length 1.231 Miles Project Type Proposition 14 Bid Date 2010-May
Work From 0.4 MI SOUTH OF SH 359/LP 20 INT Low Bid Amount $17,948,004.82
Work To 0.9 MI NORTH OF SH 359/LP 20 INT
Description CONSTRUCT OVERPASS/UNDERPASS
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Tito Gonzalez, P.E. Phone: (956) 712-7487
Construction Company LIBERTY MUTUAL INSURANCE COMPANY
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
07/22/2010 10/25/2010 733 874 106.59 % 88.46 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $879,452.24 $2,857,709.73
Construction $21,696,508.67 $17,303,452.99
Construction EngineeringConstruction Engineering Definition $897,400.24 $1,013,326.30
Contingency Contingency Definition $1,256,360.34
Indirect Indirect Definition $1,274,308.34
Total Cost $26,004,029.83 $21,174,489.02