Project ID 008501044 TxDOT District Atlanta County Name Morris Funding Status Funded
Highway US 259 Project Length 7.486 Miles Project Type Proposition 14 Bid Date 2013-Apr
Work From US 67 Low Bid Amount $7,975,983.33
Work To 0.4 MI S OF IH 30
Description REPAIR ROADWAY
Show Project Location
Contact Information
TxDOT Contact Dennis M. Beckham, P.E. Phone: (903) 799-1222
Construction Company MARTIN MARIETTA MATERIALS, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
07/23/2013 08/16/2013 360 217 57.41 % 49.13 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $390,823.18 $74,319.74
Construction $8,417,004.10 $4,641,332.57
Construction EngineeringConstruction Engineering Definition $390,823.18 $168,810.52
Contingency Contingency Definition $3,987.99
Indirect Indirect Definition $457,023.84
Total Cost $9,659,662.29 $4,884,462.83