Proposition 14 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
006201037 |
TxDOT District |
Atlanta |
County Name |
Bowie |
Funding Status |
Funded |
| Highway |
SH 8 |
Project Length |
.344 Miles |
Project Type |
Proposition 14 |
Bid Date |
2010-Mar |
| Work From |
AT INTERSECTION OF FM 2624 |
Low Bid Amount |
$1,682,976.86 |
| Work To |
. |
| Description |
CONSTRUCT CENTER TURN LANES |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Dennis M. Beckham, P.E. |
Phone: |
(903) 799-1222 |
| Construction Company |
NE-TEX CONSTRUCTION, LTD. |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
03/2009 |
04/2009 |
04/2009 |
05/2009 |
05/2009 |
05/2009 |
|
05/2009 |
| Actual Date |
03/2009 |
03/2009 |
03/2009 |
03/2009 |
03/2009 |
03/2009 |
|
03/2009 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 04/27/2010 |
06/03/2010 |
305 |
309 |
101.31 % |
104.87 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$82,158.87 |
$122,961.52 |
| Construction |
$1,755,660.90 |
$2,008,480.72 |
Construction Engineering |
$125,753.37 |
$226,381.48 |
Contingency
 |
$117,369.81 |
|
Indirect
 |
$102,447.08 |
|
| Total Cost |
$2,183,390.03 |
$2,357,823.72 |
|
 |