Proposition 14 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 006201037 TxDOT District Atlanta County Name Bowie Funding Status Funded
Highway SH 8 Project Length .344 Miles Project Type Proposition 14 Bid Date 2010-Mar
Work From AT INTERSECTION OF FM 2624 Low Bid Amount $1,682,976.86
Work To .
Description CONSTRUCT CENTER TURN LANES
Show Project Location
Contact Information
TxDOT Contact Dennis M. Beckham, P.E. Phone: (903) 799-1222
Construction Company NE-TEX CONSTRUCTION, LTD.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
04/27/2010 06/03/2010 305 309 101.31 % 104.87 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $82,158.87 $122,961.52
Construction $1,755,660.90 $2,008,480.72
Construction EngineeringConstruction Engineering Definition $125,753.37 $226,381.48
Contingency Contingency Definition $117,369.81
Indirect Indirect Definition $102,447.08
Total Cost $2,183,390.03 $2,357,823.72