Proposition 14 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 004910003 TxDOT District Waco County Name McLennan Funding Status Funded
Highway LP 574 Project Length 1.002 Miles Project Type Proposition 12 v2 Bid Date 2013-Feb
Work From BU 77 Low Bid Amount $14,436,151.22
Work To IH 35
Description CONSTRUCT NEW ROADWAY LANES
Show Project Location
Contact Information
TxDOT Contact Andy Petter, P.E. Phone: (254) 867-2740
Construction Company THE LANE CONSTRUCTION CORPORATION
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 05/2012 06/2012 07/2012 11/2012 05/2012 05/2012 11/2012
Actual Date 05/2012 07/2012 09/2012 10/2012 10/2012 10/2012 10/2012 10/2012
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $707,371.41 $496,472.93
Construction $12,203,542.77 $0.00
Construction EngineeringConstruction Engineering Definition $707,371.41 $127.79
Contingency Contingency Definition $180,451.89
Indirect Indirect Definition $626,528.96
Total Cost $14,425,266.44 $496,600.72