Proposition 14 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 004906060 TxDOT District Bryan County Name Robertson Funding Status Funded
Highway SH 6 Project Length 1.350 Miles Project Type Proposition 14 Bid Date 2009-Dec
Work From FM 1644 IN CALVERT Low Bid Amount $14,054,438.70
Work To 1.2 MILES NORTH OF MUD CREEK
Description WIDEN ROADWAY
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Bob Appleton, P.E. Phone: (979) 778-2165
Construction Company LIBERTY MUTUAL INSURANCE COMPANY
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
01/27/2010 02/10/2010 347 551 107.62 % 95.57 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $729,960.39 $1,838,806.31
Construction $14,746,041.78 $17,528,184.27
Construction EngineeringConstruction Engineering Definition $670,371.79 $976,514.28
Contingency Contingency Definition $968,314.81
Indirect Indirect Definition $844,668.45
Total Cost $17,959,357.22 $20,343,504.86