Proposition 14 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
004703076 |
TxDOT District |
Paris |
County Name |
Grayson |
Funding Status |
Funded |
| Highway |
US 75 |
Project Length |
1.150 Miles |
Project Type |
Proposition 14 |
District Est. Bid Date |
2013-Aug |
| Work From |
FM 902 |
|
|
| Work To |
SHEPHERD DRIVE |
| Description |
REBUILD ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Rick Mackey, P.E. |
Phone: |
(903) 737-9375 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
08/2012 |
10/2012 |
12/2012 |
01/2013 |
10/2012 |
10/2012 |
09/2012 |
01/2013 |
| Actual Date |
08/2012 |
10/2012 |
03/2013 |
|
08/2012 |
10/2012 |
10/2012 |
|
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$463,602.79 |
$54,361.37 |
| Construction |
$9,461,281.37 |
$0.00 |
Construction Engineering |
$463,602.79 |
$0.00 |
Contingency
 |
$4,730.64 |
|
Indirect
 |
$474,956.32 |
|
| Total Cost |
$10,868,173.91 |
$54,361.37 |
|
 |