Proposition 14 Project Detail

Data updated on: 11/10/2014 3:25 PM Print This Page
Project Summary
Project ID 004703076 TxDOT District Paris County Name Grayson Funding Status Funded
Highway US 75 Project Length 1.495 Miles Project Type Proposition 14 Bid Date 2013-Aug
Work From FM 902 Low Bid Amount $8,342,650.77
Work To SHEPHERD DRIVE
Description REBUILD ROADWAY
Show Project Location
Contact Information
TxDOT Contact Rick Mackey, P.E. Phone: (903) 737-9375
Construction Company AUSTIN BRIDGE & ROAD, LP
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
11/04/2013 01/27/2014 142 144 97.30 % 59.02 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $408,789.89 $110,968.22
Construction $9,888,731.14 $3,470,055.32
Construction EngineeringConstruction Engineering Definition $408,789.89 $79,545.66
Contingency Contingency Definition $4,171.33
Indirect Indirect Definition $418,801.07
Total Cost $11,129,283.32 $3,660,569.20