Proposition 14 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 004703076 TxDOT District Paris County Name Grayson Funding Status Funded
Highway US 75 Project Length 1.150 Miles Project Type Proposition 14 District Est. Bid Date 2013-Aug
Work From FM 902
Work To SHEPHERD DRIVE
Description REBUILD ROADWAY
Show Project Location
Contact Information
TxDOT Contact Rick Mackey, P.E. Phone: (903) 737-9375
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 08/2012 10/2012 12/2012 01/2013 10/2012 10/2012 09/2012 01/2013
Actual Date 08/2012 10/2012 03/2013 08/2012 10/2012 10/2012
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $463,602.79 $54,361.37
Construction $9,461,281.37 $0.00
Construction EngineeringConstruction Engineering Definition $463,602.79 $0.00
Contingency Contingency Definition $4,730.64
Indirect Indirect Definition $474,956.32
Total Cost $10,868,173.91 $54,361.37