Proposition 14 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
004519044 |
TxDOT District |
Paris |
County Name |
Grayson |
Funding Status |
Funded |
| Highway |
US 82 |
Project Length |
.750 Miles |
Project Type |
Proposition 14 |
Bid Date |
2010-Aug |
| Work From |
AT FM 1417 |
Low Bid Amount |
$3,606,776.26 |
| Work To |
. |
| Description |
CONSTRUCT OVERPASS/UNDERPASS |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Rick Mackey, P.E. |
Phone: |
(903) 737-9375 |
| Construction Company |
D. L. LENNON INCORPORATED - CONTRACTOR |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
05/2009 |
08/2009 |
03/2010 |
04/2010 |
04/2010 |
04/2010 |
|
04/2010 |
| Actual Date |
04/2010 |
03/2010 |
03/2010 |
03/2010 |
03/2010 |
03/2010 |
|
03/2010 |
|
|
Show Project Construction Information
|
Show Project Development Information
|
| Project Construction Information |
| Notice to Proceed Date |
Work Begin Date |
Total Project Days |
Total Days Charged |
Percentage of Time Used |
Percentage of Project Complete |
| 10/20/2010 |
11/09/2010 |
273 |
300 |
103.45 % |
106.21 % |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$176,732.04 |
$153,530.29 |
| Construction |
$4,153,975.08 |
$4,447,615.76 |
Construction Engineering |
$180,338.81 |
$137,013.56 |
Contingency
 |
$234,440.46 |
|
Indirect
 |
$229,751.65 |
|
| Total Cost |
$4,975,238.04 |
$4,738,159.61 |
|
 |