Proposition 14 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 003916063 TxDOT District Pharr County Name Cameron Funding Status Funded
Highway IH 69E Project Length .530 Miles Project Type Proposition 14 District Est. Bid Date 2014-Jun
Work From FM 802
Work To .53 MI NORTH OF FM 802
Description REPAIR ROADWAY
Show Project Location
Contact Information
TxDOT Contact Homero Bazan, P.E. Phone: (956) 702-6214
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date
Actual Date 03/2013 03/2013 06/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $208,702.68 $517,291.09
Construction $4,259,238.50 $0.00
Construction EngineeringConstruction Engineering Definition $271,739.41 $0.00
Contingency Contingency Definition $54,944.18
Indirect Indirect Definition $205,721.22
Total Cost $5,000,345.99 $517,291.09