Proposition 14 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
003401124 |
TxDOT District |
Abilene |
County Name |
Taylor |
Funding Status |
Funded |
| Highway |
US 83 |
Project Length |
3.212 Miles |
Project Type |
Proposition 14 |
District Est. Bid Date |
2013-Aug |
| Work From |
CANYON ROCK ROAD |
|
|
| Work To |
IBERIS ROAD |
| Description |
CONSTRUCT FRONTAGE ROADS |
| Project Note |
This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources. |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Blair Haynie, P.E. |
Phone: |
(325) 676-6810 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
11/2012 |
12/2012 |
02/2013 |
04/2013 |
04/2013 |
04/2013 |
04/2013 |
04/2013 |
| Actual Date |
11/2012 |
12/2012 |
02/2013 |
05/2013 |
04/2013 |
05/2013 |
05/2013 |
05/2013 |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$182,375.62 |
$207,287.64 |
| Construction |
$3,721,951.50 |
$0.00 |
Construction Engineering |
$237,460.51 |
$0.00 |
Contingency
 |
$48,013.17 |
|
Indirect
 |
$318,226.85 |
|
| Total Cost |
$4,508,027.65 |
$207,287.64 |
|
 |