Proposition 14 Project Detail

Data updated on: 6/03/2013 7:32 AM Print This Page
Project Summary
Project ID 003401124 TxDOT District Abilene County Name Taylor Funding Status Funded
Highway US 83 Project Length 3.212 Miles Project Type Proposition 14 District Est. Bid Date 2013-Aug
Work From CANYON ROCK ROAD
Work To IBERIS ROAD
Description CONSTRUCT FRONTAGE ROADS
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Blair Haynie, P.E. Phone: (325) 676-6810
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 11/2012 12/2012 02/2013 04/2013 04/2013 04/2013 04/2013 04/2013
Actual Date 11/2012 12/2012 02/2013 05/2013 04/2013 05/2013 05/2013 05/2013
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $182,375.62 $207,287.64
Construction $3,721,951.50 $0.00
Construction EngineeringConstruction Engineering Definition $237,460.51 $0.00
Contingency Contingency Definition $48,013.17
Indirect Indirect Definition $318,226.85
Total Cost $4,508,027.65 $207,287.64