Proposition 14 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 001619023 TxDOT District San Antonio County Name Comal Funding Status Funded
Highway FM 482 Project Length 4.218 Miles Project Type Proposition 14 Bid Date 2012-Apr
Work From 0.4 MI SW OF KRUEGER CANYON RD. Low Bid Amount $3,882,623.18
Work To FM 2252
Description WIDEN ROADWAY
Show Project Location
Contact Information
TxDOT Contact Gregg Granato, P.E. Phone: (210) 615-6049
Construction Company ANGEL BROTHERS ENTERPRISES, LTD.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
06/21/2012 09/24/2012 341 188 55.13 % 100.66 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $190,248.54 $452,767.21
Construction $4,348,512.67 $4,200,537.12
Construction EngineeringConstruction Engineering Definition $181,239.13 $184,744.30
Contingency Contingency Definition $893.71
Indirect Indirect Definition $265,959.69
Total Cost $4,986,853.74 $4,838,048.63