Proposition 14 Project Detail

Data updated on: 4/02/2014 8:12 AM Print This Page
Project Summary
Project ID 001407083 TxDOT District Waco County Name Hill Funding Status Funded
Highway IH 35 Project Length 5.456 Miles Project Type Proposition 14 Bid Date 2010-Apr
Work From FM 1304 Low Bid Amount $36,044,760.95
Work To FM 310
Description CONSTRUCT NEW ROADWAY LANES
Show Project Location
Contact Information
TxDOT Contact Andy Petter, P.E. Phone: (254) 867-2740
Construction Company W.W. WEBBER, LLC
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
06/24/2010 07/12/2010 638 658 99.25 % 98.27 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $1,648,279.05 $1,781,194.09
Construction $42,786,378.59 $35,225,887.47
Construction EngineeringConstruction Engineering Definition $1,513,725.66 $1,285,564.48
Contingency Contingency Definition $3,027,451.32
Indirect Indirect Definition $2,627,154.97
Total Cost $51,602,989.59 $38,292,646.04