Proposition 14 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
000404083 |
TxDOT District |
Odessa |
County Name |
Ward |
Funding Status |
Funded |
| Highway |
IH 20 |
Project Length |
.909 Miles |
Project Type |
Traditional |
District Est. Bid Date |
2013-Jun |
| Work From |
NEAR SH 18 |
|
|
| Work To |
. |
| Description |
CONSTRUCT FREEWAY RAMPS |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Gary J. Law, P.E. |
Phone: |
(432) 332-0501 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
07/2012 |
11/2012 |
12/2012 |
03/2013 |
11/2013 |
09/2012 |
09/2012 |
11/2013 |
| Actual Date |
07/2012 |
01/2013 |
02/2013 |
|
|
03/2013 |
07/2012 |
|
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$100,663.12 |
$182,706.26 |
| Construction |
$2,054,349.30 |
$0.00 |
Construction Engineering |
$123,055.52 |
$0.00 |
Contingency
 |
$53,413.08 |
|
Indirect
 |
$171,538.17 |
|
| Total Cost |
$2,503,019.19 |
$182,706.26 |
|
 |