Proposition 12 v2 Project Detail

Data updated on: 7/06/2015 12:45PM Print This Page
Project Summary
Project ID 817012001 TxDOT District Houston County Name Harris Funding Status Unfunded
Highway MH Project Length 1.023 Miles Project Type Traditional District Est. Bid Date 2016-Jun
Work From ON HEMPSTEAD RD, 0.059 MI W OF 12
Work To ST TO E OF WASHINGTON-KATY SPLIT
Description CONSTRUCT NEW ROADWAY LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Pamela Elmer, P.E. Phone: (713) 802-5646
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 09/2011 04/2012 12/2012 08/2013 11/2012 08/2014 08/2014 08/2014
Actual Date 10/2010 01/2012 08/2014 10/2010 04/2015
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $2,669,331.77 $6,303,459.30
Construction $54,476,158.59 $35,128.42
Construction EngineeringConstruction Engineering Definition $2,702,017.47 $0.00
Contingency Contingency Definition $1,084,075.56
Indirect Indirect Definition NaN
Total Cost $60,931,583.39 $6,338,587.72