Proposition 12 v2 Project Detail

Data updated on: 3/04/2015 11:09AM Print This Page
Project Summary
Project ID 305002025 TxDOT District Houston County Name Montgomery Funding Status Funded
Highway FM 2978 Project Length 2.500 Miles Project Type Traditional District Est. Bid Date 2015-Oct
Work From CONROE HUFFSMITH
Work To S OF DRY CREEK
Description WIDEN ROADWAY
Show Project Location
Contact Information
TxDOT Contact Pamela Elmer, P.E. Phone: (713) 802-5646
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date 05/2013 07/2013 01/2014 05/2014 10/2013 05/2014 03/2014 05/2014
Actual Date 05/2012 07/2012
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $221,253.81 $624,193.34
Construction $4,515,383.90 $0.00
Construction EngineeringConstruction Engineering Definition $223,963.04 $0.00
Contingency Contingency Definition $89,856.14
Indirect Indirect Definition $259,183.04
Total Cost $5,309,639.93 $624,193.34