Proposition 12 v2 Project Detail

Data updated on: 5/07/2013 8:55 AM Print This Page
Project Summary
Project ID 294101022 TxDOT District Houston County Name Harris Funding Status Funded
Highway FM 2920 Project Length 1.645 Miles Project Type Proposition 12 v2 Bid Date 2012-Jul
Work From 0.2 MI W OF KICKAPOO RD(IN SECTION) Low Bid Amount $3,658,493.97
Work To 0.2 MI E OF ROSEWOOD TRAIL
Description CONSTRUCT INTERSECTION IMPROVEMENTS
Show Project Location
Contact Information
TxDOT Contact Bill Brudnick, P.E. Phone: (713) 802-5617
Construction Company DURWOOD GREENE CONSTRUCTION CO.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
09/13/2012 10/02/2012 160 123 76.88 % 74.17 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $179,266.20 $418,352.67
Construction $3,486,689.12 $2,816,727.98
Construction EngineeringConstruction Engineering Definition $219,509.64 $98,732.35
Contingency Contingency Definition $47,194.57
Indirect Indirect Definition $254,997.03
Total Cost $4,187,656.56 $3,333,813.00