Proposition 12 v2 Project Detail

Data updated on: 9/02/2014 11:01AM Print This Page
Project Summary
Project ID 229301023 TxDOT District Austin County Name Hays Funding Status Funded
Highway FM 2439 Project Length .100 Miles Project Type Proposition 12 v2 Bid Date 2013-Aug
Work From CENTERPOINT ROAD Low Bid Amount $2,961,890.34
Work To POSEY ROAD
Description CONSTRUCT CENTER TURN LANES
Project Note This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources.
Show Project Location
Contact Information
TxDOT Contact Walter Barfield, P.E. Phone: (512) 832-7136
Construction Company DEAN WORD COMPANY, LTD.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
01/06/2014 03/08/2014 95 113 118.95 % 70.95 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $116,401.32 $500,343.41
Construction $2,373,880.10 $1,477,064.88
Construction EngineeringConstruction Engineering Definition $116,401.32 $87,242.34
Contingency Contingency Definition $1,187.77
Indirect Indirect Definition $137,543.60
Total Cost $2,745,414.11 $2,064,650.63