Proposition 12 v2 Project Detail

Data updated on: 8/01/2014 2:38 PM Print This Page
Project Summary
Project ID 228401028 TxDOT District San Angelo County Name Tom Green Funding Status Funded
Highway FM 388 Project Length 2.169 Miles Project Type Proposition 12 v2 Bid Date 2013-Jul
Work From BELL STREET Low Bid Amount $2,261,709.25
Work To 350 FEET WEST OF SL 306
Description CONSTRUCT NEW ROADWAY LANES
Show Project Location
Contact Information
TxDOT Contact Gary Enos, P.E. Phone: (325) 947-9233
Construction Company REECE ALBERT, INC.
Project Construction Information
Notice to Proceed Date Work Begin Date Total Project Days Total Days Charged Percentage of Time Used Percentage of Project Complete
10/21/2013 11/04/2013 132 144 109.09 % 92.34 %
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $59,709.12 $114,097.03
Construction $1,893,460.97 $2,344,062.05
Construction EngineeringConstruction Engineering Definition $104,717.14 $96,685.73
Contingency Contingency Definition $24,426.46
Indirect Indirect Definition $217,802.60
Total Cost $2,300,116.29 $2,554,844.81