Proposition 12 v2 Project Detail

Data updated on: 6/03/2013 7:32 AM Print This Page
Project Summary
Project ID 207502045 TxDOT District Tyler County Name Smith Funding Status Funded
Highway LP 323 Project Length .637 Miles Project Type Proposition 12 v2 District Est. Bid Date 2013-Aug
Work From 0.6 MI S OF SH 31 (SHAW ST), N
Work To SH 31 (W) IN TYLER
Description REPLACE BRIDGE
Show Project Location
Contact Information
TxDOT Contact Vernon Webb, P.E. Phone: (903) 510-9296
Project Development Milestones
Start Design Design Submittal Receive Environmental ClearanceReceive Environmental Clearance Definition Utility CoordinationUtility Coordination Definition Right of Way CoordinationRight of Way Coordination Definition Project Ready to BidProject Ready to Bid Definition
30% Complete30% Complete Definition 60% Complete60% Complete 100% Complete100% Complete Definition
Target Date
Actual Date 01/2007 06/2012 11/2012
Budget Information
Project Cost Current Estimate Amount Paid to Date
Project EngineeringProject Engineering Definition $483,221.43 $893,912.95
Construction $9,861,661.79 $0.00
Construction EngineeringConstruction Engineering Definition $727,354.36 $0.00
Contingency Contingency Definition $23,352.79
Indirect Indirect Definition $534,502.07
Total Cost $11,630,092.44 $893,912.95