Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
168507019 |
TxDOT District |
Houston |
County Name |
Harris |
Funding Status |
Funded |
| Highway |
BF1960A |
Project Length |
4.200 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-Aug |
| Work From |
LEE ROAD |
|
|
| Work To |
FM 1960(E) |
| Description |
RESURFACE ROADWAY |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Bill Brudnick, P.E. |
Phone: |
(713) 802-5617 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
12/2011 |
06/2012 |
11/2012 |
03/2013 |
07/2013 |
03/2013 |
03/2013 |
07/2013 |
| Actual Date |
12/2011 |
06/2012 |
03/2013 |
|
|
|
|
|
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$503,738.43 |
$1,287,723.40 |
| Construction |
$10,280,376.23 |
$0.00 |
Construction Engineering |
$434,636.82 |
$0.00 |
Contingency
 |
$192,373.57 |
|
Indirect
 |
$486,261.79 |
|
| Total Cost |
$11,897,386.84 |
$1,287,723.40 |
|
 |