Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
138401021 |
TxDOT District |
Atlanta |
County Name |
Titus |
Funding Status |
Funded |
| Highway |
FM 1402 |
Project Length |
.639 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-Aug |
| Work From |
1.2 MI N OF IH 30 |
|
|
| Work To |
1.8 MI N OF IH 30 |
| Description |
CONSTRUCT CENTER TURN LANES |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Dennis M. Beckham, P.E. |
Phone: |
(903) 799-1222 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
09/2011 |
09/2011 |
09/2011 |
11/2011 |
09/2011 |
10/2011 |
10/2011 |
11/2011 |
| Actual Date |
08/2011 |
12/2011 |
08/2012 |
|
06/2012 |
|
|
|
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$69,864.02 |
$365,134.52 |
| Construction |
$1,425,796.39 |
$0.00 |
Construction Engineering |
$69,864.02 |
$0.00 |
Contingency
 |
$17,822.45 |
|
Indirect
 |
$81,698.13 |
|
| Total Cost |
$1,665,045.01 |
$365,134.52 |
|
 |