Proposition 12 v2 Project Detail
Return to: Report List Page

| Project Summary |
| Project ID |
137802039 |
TxDOT District |
Austin |
County Name |
Williamson |
Funding Status |
Funded |
| Highway |
RM 1431 |
Project Length |
2.492 Miles |
Project Type |
Proposition 12 v2 |
District Est. Bid Date |
2013-Aug |
| Work From |
ANDERSON MILL RD |
|
|
| Work To |
600 FT WEST OF 183A |
| Description |
CONSTRUCT INTERSECTION IMPROVEMENTS |
| Project Note |
This project is being developed by non-TxDOT resources. Estimates have been provided to TxDOT by these resources. |
|
Show Project Location
|
|
 |
| Contact Information |
| TxDOT Contact |
Walter Barfield, P.E. |
Phone: |
(512) 832-7136 |
|
 |
| Project Development Milestones |
|
Start Design |
Design Submittal |
Receive Environmental Clearance |
Utility Coordination |
Right of Way Coordination |
Project Ready to Bid |
30% Complete |
60% Complete |
100% Complete |
| Target Date |
02/2012 |
10/2012 |
12/2012 |
03/2013 |
06/2013 |
03/2013 |
02/2013 |
06/2013 |
| Actual Date |
02/2012 |
10/2012 |
12/2012 |
03/2013 |
03/2013 |
04/2013 |
04/2013 |
04/2013 |
|
| |
| Budget Information |
| Project Cost |
Current Estimate |
Amount Paid to Date |
Project Engineering |
$201,708.96 |
$519,902.30 |
| Construction |
$4,116,509.35 |
$0.00 |
Construction Engineering |
$262,633.30 |
$0.00 |
Contingency
 |
$53,102.97 |
|
Indirect
 |
$238,345.89 |
|
| Total Cost |
$4,872,300.47 |
$519,902.30 |
|
 |